Site Reference: Revenue Commissioners Offices, Newcastle West, Limerick
Description: Following the Decentralisation announcement in Budget 2004, the Office of Public Works scheduled the decentralisation of the Revenue Commissioners Offices to Newcastle West, Limerick.
No. of Units: 2
Consultant: Arups Consulting Engineers
Architect: John Thompson & Partners
Main Contractor: Frank McGrath Construction Ltd
No. of floors: 2
Lifts:
Capacity: 2 x 630kg / 8 Person
Type: Orona M33 Electric Traction Passenger Lifts
Drive: Gearless Electric traction, Machine room less (MRL)
Site Reference: Revenue Commissioners Offices, Sarsfield House, Limerick
Description: In 2007 the Office of Public Works went out to tender the refurbishment work at Sarsfield House, Francis Street, Limerick City. Mid Western Lifts Ltd were sucessful. The refurbishment consisted of 4 side drive traction lifts being completly replaced with modern machine room less traction drive units. Also the refurbhishment of an old two floor Hydraulic passenger lift with travel of 11 meters. We replaced the motor, controller, doors and lift car.
No. of Units: 5
Consultant: The Office of Public Works
Architect: The Office of Public Works
Main Contractor: Mid Western Lift Services Ltd
No. of floors: 7
Lifts:
Capacity: 4 x 800kg / 10 Person
Type: Kleemann Atlas Traction Passenger Lifts
Drive: Gearless Electric traction, Machine room less (MRL)